Installation and Operation Manual
Check the flush duration (default is 1 minute).
Check the RH set point and set at the desired level.
Confirm that the control input signal is consistent with the
Vapor-logic
3
configuration string. Identify the factory-set
Vapor-logic
3
configuration string on the wiring diagram or on
the outside of the control cabinet door. Refer to the configuration
string descriptions on Pages 32 and 33.
Confirm that all wiring is correct per the wiring diagram.
Confirm that proper grounding and an approved earth ground
are provided.
Confirm that the analog inputs are configured properly by
verifying that J14/J17, J15/J18, and J16/J19 shunt connectors
on the Vapor-logic
3
board are in their correct position per the
wiring diagram. See Pages 11 and 13 for the physical locations.
Confirm that the keypad/display is mounted with modular cable
routed away from high voltage circuits and connected to the J2
female connector on the Vapor-logic
3
board.
Turn water supply on and confirm that the drain valve is closed.
Turn power on and confirm that the display shows the Main
Menu screen with an operational clock.
Enter the Control Modes screen and make sure the system is in
auto mode.
When “Filling” appears on the status line of the Idle screen,
confirm that the tank is filling with water.
Confirm that the airflow switch is closed.
More on next page ▶
Start-up checklist, continued
Start-up checklist (continued)